DGL completed the design phase for this project as well as construction administration and construction inspection for the full construction duration. The project, located at Clifton-Gunn Road (MP 21.4), Rueger-Shetler Road Bridge (MP 23.9), Fulton-Williams Road (MP 24.4) and the Spies-Handy Corners Road Bridge (MP 27.3 over the turnpike), included replacing the bridge decks and abutment slabs, deck joints and bearings and installing fencing. Substantial completion of the project was on time and under budget. The original construction cost for this project was $3.20 million.